Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a very complex project with over 100 resources. You need to ensure that all tasks are assigned to…

The correct answer is C. Use Resource Usage view and look for the Unassigned resource name. See the full explanation below for the reasoning.

Question

Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a very complex project with over 100 resources. You need to ensure that all tasks are assigned to resources. What should you do?

Options

  • AUse Task Usage view and look for Unassigned tasks.
  • BUse Resource Graph view and look for the Unassigned resource name.
  • CUse Resource Usage view and look for the Unassigned resource name.
  • DUse Resource Sheet view and look for Unassigned tasks.

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    83% (24)
  • D
    3% (1)