74-343 · Question #88

You manage a project by using Project Professional 2013. Your project is updated with changes to the baseline for selected tasks. You back up your project fife before you start your next tracking…

The correct answer is D. Reset the baseline checking the Roll up baselines to all summary tasks option. See the full explanation below for the reasoning.

Question

You manage a project by using Project Professional 2013. Your project is updated with changes to the baseline for selected tasks. You back up your project fife before you start your next tracking cycle. After completing the tracking cycle, you notice that the baseline duration values on some of the summary tasks are not correct. You need to correct these values before re-entering the tracking data. You open the backed up version of the project schedule. What should you do next?

Options

  • AManually update the summary tasks with the new duration values.
  • BReset the summary tasks to manual scheduling.
  • CEnsure the tasks durations are of the same denomination values.
  • DReset the baseline checking the Roll up baselines to all summary tasks option.

How the community answered

(30 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    7% (2)
  • D
    77% (23)