74-343 · Question #87
You use Project Professional 2013 to manage a project that has customer-required milestone completion dates. You need to see graphically that your milestones have slipped beyond your…
The correct answer is C. a deadline. See the full explanation below for the reasoning.
Question
You use Project Professional 2013 to manage a project that has customer-required milestone completion dates. You need to see graphically that your milestones have slipped beyond your customer-required dates. What should you add to the project milestones?
Options
- Aa Must finish on constraint
- Ba finish date
- Ca deadline
- Da Finish no later than constraint
How the community answered
(54 responses)- A4% (2)
- B17% (9)
- C72% (39)
- D7% (4)