You use Project Professional 2013 to manage a project that has customer-required milestone completion dates. You need to see graphically that your milestones have slipped beyond your…

The correct answer is C. a deadline. See the full explanation below for the reasoning.

Question

You use Project Professional 2013 to manage a project that has customer-required milestone completion dates. You need to see graphically that your milestones have slipped beyond your customer-required dates. What should you add to the project milestones?

Options

  • Aa Must finish on constraint
  • Ba finish date
  • Ca deadline
  • Da Finish no later than constraint

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    17% (9)
  • C
    72% (39)
  • D
    7% (4)

Community Discussion

No community discussion yet for this question.