74-343 · Question #54
You are a project manager, and you use Project 2013 for a large construction project. You create the work breakdown structure (WBS) and plan to add the following resources for your project…
The correct answer is B. Add Cost Resources. D. Add Material Resources. See the full explanation below for the reasoning.
Question
You are a project manager, and you use Project 2013 for a large construction project. You create the work breakdown structure (WBS) and plan to add the following resources for your project: concrete, construction supplies, and airline tickets. You need to add these resources to your schedule. Which two resource types should be created for these resource examples? (Each correct answer presents part of the solution. Choose two.)
Options
- AAdd Generic Resources.
- BAdd Cost Resources.
- CAdd Work Resources.
- DAdd Material Resources.
How the community answered
(41 responses)- A7% (3)
- B78% (32)
- C15% (6)