Sign in or unlock 74-343 to reveal the answer and full explanation for question #54. The question stem and answer options stay visible for context.
Question
You are a project manager, and you use Project 2013 for a large construction project. You create the work breakdown structure (WBS) and plan to add the following resources for your project: concrete, construction supplies, and airline tickets. You need to add these resources to your schedule. Which two resource types should be created for these resource examples? (Each correct answer presents part of the solution. Choose two.)
Options
- AAdd Generic Resources.
- BAdd Cost Resources.
- CAdd Work Resources.
- DAdd Material Resources.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.