74-343 · Question #53
You are an independent project manager who uses Project Professional 2013. You work on multiple projects for different customers and use only one project to manage their tasks. You invoice your…
The correct answer is C. Apply the custom filter and select the Highlight option. See the full explanation below for the reasoning.
Question
You are an independent project manager who uses Project Professional 2013. You work on multiple projects for different customers and use only one project to manage their tasks. You invoice your customers on a monthly basis. To identify tasks that have not been invoiced, you create a custom field called Not Invoiced. Without losing the original project tasks' sort order, and without hiding any information, you need to see all tasks which have not been invoiced. You create a custom filter based on the Not Invoiced custom field. What should you do next?
Options
- AApply the custom filter.
- BExport to Microsoft Excel using the custom filter.
- CApply the custom filter and select the Highlight option
- DUse the filter in the Group By function.
How the community answered
(61 responses)- A11% (7)
- B3% (2)
- C80% (49)
- D5% (3)
Community Discussion
No community discussion yet for this question.