An Agile Release Train (ART) is frequently discovering compatibility issues between the developed Solution and the Enterprise information architecture. What can the Release Train Engineer do to prevent this from occurring?
Options
- ADevelop more detailed Feature definitions
- BAdd data Architects onto the ART
- CConfirm attendance of architectural representatives at Program Increment (PI) Planning
- DConduct the entire data architecture design upfront
How the community answered
(22 responses)- A9% (2)
- B5% (1)
- C82% (18)
- D5% (1)