What are two main reasons why the program predictability measure is important? (Choose two.)
The correct answer is B. It identifies under-performing teams C. It focuses the Agile Release Train on predictable value delivery. See the full explanation below for the reasoning.
Question
What are two main reasons why the program predictability measure is important? (Choose two.)
Options
- AIt allows the business and other stakeholders to plan effectively
- BIt identifies under-performing teams
- CIt focuses the Agile Release Train on predictable value delivery
- DIt demonstrates the need to fix the scope at the beginning of the Program Increment (PI)
- EIt indicates whether the Solution is ready to be released
How the community answered
(18 responses)- A6% (1)
- B83% (15)
- E11% (2)