SAFE-RTE · Question #151
Sometimes the Scrum of Scrums and PO Sync can be combined into one meeting. What is this meeting called?
The correct answer is A. ART Sync. See the full explanation below for the reasoning.
Question
Sometimes the Scrum of Scrums and PO Sync can be combined into one meeting. What is this meeting called?
Options
- AART Sync
- BSoS Sync
- CPI Sync
- DIteration Sync
How the community answered
(47 responses)- A85% (40)
- B2% (1)
- C4% (2)
- D9% (4)