SAFE-RTE · Question #152

Which three activities are considered to be a Team Event? (Choose three.)

The correct answer is A. Daily Stand-up C. Iteration Planning D. Backlog Refinement. See the full explanation below for the reasoning.

Question

Which three activities are considered to be a Team Event? (Choose three.)

Options

  • ADaily Stand-up
  • BSystem Demo
  • CIteration Planning
  • DBacklog Refinement
  • EScrum of Scrums
  • FInspect and Adapt

How the community answered

(31 responses)