SAFE-RTE · Question #147

SAFE-RTE Question #147: Real Exam Question with Answer & Explanation

The correct answer is C. All Feature delivery and dependencies are visualized on the program board. See the full explanation below for the reasoning.

Question

Which activity takes place during Team Breakout #2 on the second day of Program In-crement (PI) Planning?

Options

  • AThe RTE modifies the PI Iteration schedule, if needed, based on the scope of high priority
  • BBusiness Owners assign business value without team discussion so they can nor-malize business
  • CAll Feature delivery and dependencies are visualized on the program board
  • DThe Release Train Engineer (RTE) combines all Team PI Objectives into Program PI Objectives