nerdexam
Scaled_Agile

SAFE-RTE · Question #90

What are the three key items communicated on the Program Board? (Choose three.)

The correct answer is A. Feature delivery dates D. Milestones E. Dependencies between teams. See the full explanation below for the reasoning.

Question

What are the three key items communicated on the Program Board? (Choose three.)

Options

  • AFeature delivery dates
  • BPI Objectives
  • CProgram risks
  • DMilestones
  • EDependencies between teams
  • FTeam velocity

How the community answered

(54 responses)
  • A
    76% (41)
  • B
    4% (2)
  • C
    7% (4)
  • F
    13% (7)

Community Discussion

No community discussion yet for this question.

Full SAFE-RTE Practice