What action does a Release Train Engineer take prior to an upcoming Program Incre-ment (PI) Planning meeting?

The correct answer is C. Facilitate Product Management and other stakeholders in prioritization of the Pro-gram Backlog. See the full explanation below for the reasoning.

Question

What action does a Release Train Engineer take prior to an upcoming Program Incre-ment (PI) Planning meeting?

Options

  • AProvide approval and sign-off for draft Team Backlogs
  • BAllocate time in the scrum of scrums meeting for Product Management to social-ize with the teams
  • CFacilitate Product Management and other stakeholders in prioritization of the Pro-gram Backlog
  • DEnsure that at least 30% of the Program Backlog is allocated to Enabler Features

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    5% (2)
  • C
    81% (34)
  • D
    12% (5)

Community Discussion

No community discussion yet for this question.