SAFE-RTE · Question #92

When planning for a distributed Program Increment (PI) Planning event with a large dif-ference in time zones, what are two key preparation and facilitation focus areas for a Re-lease Train Engineer…

The correct answer is C. Adjust the PI agenda to 2.5 ?3 days, allowing for overlapping hours E. Arrange and test presentation audio and video connectivity in all locations. See the full explanation below for the reasoning.

Question

When planning for a distributed Program Increment (PI) Planning event with a large dif-ference in time zones, what are two key preparation and facilitation focus areas for a Re-lease Train Engineer (RTE)? (Choose two.)

Options

  • AShare the outcomes of preparation meetings with local Scrum Masters so they can arrange local
  • BHave a single RTE and technical support person that acts as a central point of communication for
  • CAdjust the PI agenda to 2.5 ?3 days, allowing for overlapping hours
  • DSplit up the PI Planning event per time zone and then have the final plan review, confidence vote,
  • EArrange and test presentation audio and video connectivity in all locations

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    16% (5)
  • C
    74% (23)
  • D
    3% (1)