What are two ways to ensure facility readiness when preparing for the Program Incre-ment (PI) Planning event? (Choose two.)
The correct answer is A. Secure communication channels for remote participants C. Engage audio-visual technical support. See the full explanation below for the reasoning.
Question
What are two ways to ensure facility readiness when preparing for the Program Incre-ment (PI) Planning event? (Choose two.)
Options
- ASecure communication channels for remote participants
- BPrint program boards
- CEngage audio-visual technical support
- DShare business value documents
- EPrint PI Objectives
How the community answered
(47 responses)- A79% (37)
- B11% (5)
- D4% (2)
- E6% (3)