During Pl Planning, who owns the planning of Stories into Iterations?

The correct answer is A. Agile Teams. See the full explanation below for the reasoning.

Question

During Pl Planning, who owns the planning of Stories into Iterations?

Options

  • AAgile Teams
  • BScrum Master
  • CProduct Management
  • DSystem Architect

How the community answered

(45 responses)
  • A
    76% (34)
  • B
    7% (3)
  • C
    13% (6)
  • D
    4% (2)