SAFE-RTE · Question #104
What falls outside the Scrum Master's responsibility? (Choose two.)
The correct answer is A. Estimating Stories for the team B. Assigning Stories to team members. See the full explanation below for the reasoning.
Question
What falls outside the Scrum Master's responsibility? (Choose two.)
Options
- AEstimating Stories for the team
- BAssigning Stories to team members
- CFacilitating backlog refinement
- DFacilitating the team's Innovation and Planning event
- ECoaching the team
How the community answered
(48 responses)- A79% (38)
- C4% (2)
- D13% (6)
- E4% (2)
Community Discussion
No community discussion yet for this question.