SAFE-RTE · Question #107

Which statement is true about estimating Features using Story points?

The correct answer is A. More than one team may be involved in the estimation. See the full explanation below for the reasoning.

Question

Which statement is true about estimating Features using Story points?

Options

  • AMore than one team may be involved in the estimation
  • BT-shirt sizing is the best way to estimate features
  • CFeature estimation is performed solely by Product Managers

How the community answered

(22 responses)
  • A
    82% (18)
  • B
    14% (3)
  • C
    5% (1)