A program is completed and the expected benefits are realized Before executing the transition and closing of the program, what should the program manager do?
The correct answer is C. Obtain approval from the program governance board to initiate program closure activities. See the full explanation below for the reasoning.
Program Governance
Question
A program is completed and the expected benefits are realized Before executing the transition and closing of the program, what should the program manager do?
Options
- ACreate a final program report.
- BArchive documents and lessons learned
- CObtain approval from the program governance board to initiate program closure activities
- DPerform administrative and program management information system (PMIS) closure activities.
How the community answered
(26 responses)- A15% (4)
- B8% (2)
- C73% (19)
- D4% (1)
Topics
#program closure#governance board approval#program transition#closure activities