The correct answer is A. Program management plan. See the full explanation below for the reasoning.

Question

A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects. Where should the program manager incorporate this input?

Options

  • AProgram management plan
  • BStakeholder register
  • CVendor management matrix
  • DProgram risk management plan