The correct answer is A. Program management plan. See the full explanation below for the reasoning.
Question
A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects. Where should the program manager incorporate this input?
Options
- AProgram management plan
- BStakeholder register
- CVendor management matrix
- DProgram risk management plan
Community Discussion