A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little…

The correct answer is B. Revisit assignments on a weekly basis to manually level resources thereby limiting burn-out and. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives. What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?

Options

  • ARequire project managers to perform resource levelling in their schedules to automatically take
  • BRevisit assignments on a weekly basis to manually level resources thereby limiting burn-out and
  • COptimize integration of the component projects by working with the project managers to align
  • DImprove communications between the project managers to gain efficiencies in resource

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    76% (28)
  • C
    14% (5)
  • D
    5% (2)

Topics

#resource leveling#global program management#resource management#schedule management