RCDDV15 · Question #121
What actions are taken in the process of developing and maintaining a program risk register?
The correct answer is B. Assign ownership of risks with appropriate responsibilities, document agreed-upon response. See the full explanation below for the reasoning.
Program Governance
Question
What actions are taken in the process of developing and maintaining a program risk register?
Options
- AAssign ownership of risks with appropriate responsibilities, document agreed-upon response
- BAssign ownership of risks with appropriate responsibilities, document agreed-upon response
- CAssign ownership of risks with appropriate responsibilities, document agreed-upon response
- DAssign ownership of risks with appropriate responsibilities, document agreed-upon response
How the community answered
(44 responses)- A5% (2)
- B70% (31)
- C7% (3)
- D18% (8)
Topics
#risk register#risk ownership#risk response documentation#program risk management