RCDDV15 · Question #121

What actions are taken in the process of developing and maintaining a program risk register?

The correct answer is B. Assign ownership of risks with appropriate responsibilities, document agreed-upon response. See the full explanation below for the reasoning.

Program Governance

Question

What actions are taken in the process of developing and maintaining a program risk register?

Options

  • AAssign ownership of risks with appropriate responsibilities, document agreed-upon response
  • BAssign ownership of risks with appropriate responsibilities, document agreed-upon response
  • CAssign ownership of risks with appropriate responsibilities, document agreed-upon response
  • DAssign ownership of risks with appropriate responsibilities, document agreed-upon response

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    70% (31)
  • C
    7% (3)
  • D
    18% (8)

Topics

#risk register#risk ownership#risk response documentation#program risk management