RCDD-002 · Question #2

Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?

The correct answer is A. PERT. PERT (Program Evaluation and Review Technique) is correct because it explicitly models tasks as a network of nodes connected by dependency arrows, making predecessor/successor relationships the core of how it works - you cannot build a PERT chart without defining what comes…

ICT Design Fundamentals and Project Management

Question

Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?

Options

  • APERT
  • BCalendar
  • CMilestone
  • DGantt

How the community answered

(24 responses)
  • A
    75% (18)
  • B
    17% (4)
  • C
    4% (1)
  • D
    4% (1)

Explanation

PERT (Program Evaluation and Review Technique) is correct because it explicitly models tasks as a network of nodes connected by dependency arrows, making predecessor/successor relationships the core of how it works - you cannot build a PERT chart without defining what comes before and after each activity. A Gantt chart shows tasks on a timeline with bars indicating duration, but does not inherently encode dependencies (though modern tools can overlay them, the chart type itself is not dependency-based). A Milestone chart only marks key events or deliverables, with no representation of task relationships at all. A Calendar chart simply maps tasks to calendar dates without any dependency logic.

Memory tip: Think "PERT = Predecessor/Successor chain" - the P in PERT can remind you of predecessors, and the network diagram it produces looks like a chain of connected nodes flowing from start to finish.

Topics

#PERT#scheduling charts#predecessor-successor relationships#project management