PSM-II · Question #98
Which of the following are feedback loops in Scrum?
The correct answer is A. Daily Scrum, Sprint Review, and Sprint Retrospective. Option A is correct because Daily Scrum, Sprint Review, and Sprint Retrospective are the three official Scrum ceremonies that function as feedback loops - they create inspect-and-adapt cycles at different cadences (daily, end-of-sprint for the product, and end-of-sprint for the…
Question
Which of the following are feedback loops in Scrum?
Options
- ADaily Scrum, Sprint Review, and Sprint Retrospective
- BDaily Standup, Sprint Review, and Sprint Retrospective
- CRelease Planning, Daily Scrum, and Sprint Review
- DGrooming, Daily Status, and Sprint Review
How the community answered
(53 responses)- A91% (48)
- B2% (1)
- C6% (3)
- D2% (1)
Explanation
Option A is correct because Daily Scrum, Sprint Review, and Sprint Retrospective are the three official Scrum ceremonies that function as feedback loops - they create inspect-and-adapt cycles at different cadences (daily, end-of-sprint for the product, and end-of-sprint for the team process).
B is wrong because "Daily Standup" is an informal/common name, not the official Scrum Guide term. Scrum uses "Daily Scrum" - exams test precise terminology.
C is wrong because "Release Planning" is not a Scrum event. Sprint Planning is, but it's an input/planning ceremony, not a feedback loop in the Scrum framework.
D is wrong on two counts: "Grooming" (now called Backlog Refinement) is not a formal Scrum event, and "Daily Status" doesn't exist in Scrum at all.
Memory tip: Think D-R-R - Daily Scrum (daily feedback), Review (product feedback), Retrospective (process feedback). All three use the official Scrum Guide names, and each answers a different question: Are we on track today? Did we build the right thing? How do we improve our process?