PSM-II · Question #97

Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

The correct answer is B. False. Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.

Scaling Scrum

Question

Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

Options

  • ATrue
  • BFalse

How the community answered

(42 responses)
  • A
    10% (4)
  • B
    90% (38)

Explanation

Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.

Topics

#multiple Scrum Teams#Sprint synchronization#scaling