nerdexam
Scrum

PSM-II · Question #97

PSM-II Question #97: Real Exam Question with Answer & Explanation

The correct answer is B. False. Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.

Question

Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

Options

  • ATrue
  • BFalse

Explanation

Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.

Community Discussion

No community discussion yet for this question.

Full PSM-II Practice
Multiple Scrum Teams working from the same Product Backlog must... | PSM-II Q#97 Answer | NerdExam