Scrum
PSM-II · Question #97
PSM-II Question #97: Real Exam Question with Answer & Explanation
The correct answer is B. False. Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.
Question
Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.
Options
- ATrue
- BFalse
Explanation
Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.
Community Discussion
No community discussion yet for this question.