PSM-II · Question #83

Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?

The correct answer is B. The Development Team. The Development Team is responsible for tracking the remaining work of the Sprint.

Applying Scrum

Question

Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?

Options

  • AThe Product Owner
  • BThe Development Team
  • CThe Scrum Team
  • DThe Scrum Master

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    91% (32)
  • D
    6% (2)

Explanation

The Development Team is responsible for tracking the remaining work of the Sprint.

Topics

#Sprint Backlog#Development Team#accountability