Scrum
PSM-II · Question #83
Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?
The correct answer is B. The Development Team. The Development Team is responsible for tracking the remaining work of the Sprint.
Applying Scrum
Question
Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?
Options
- AThe Product Owner
- BThe Development Team
- CThe Scrum Team
- DThe Scrum Master
How the community answered
(35 responses)- A3% (1)
- B91% (32)
- D6% (2)
Explanation
The Development Team is responsible for tracking the remaining work of the Sprint.
Topics
#Sprint Backlog#Development Team#accountability
Community Discussion
No community discussion yet for this question.