PSM-II · Question #82

Every Development Team should have the competencies and skills needed to deliver a Done Increment in a Sprint.

The correct answer is A. True. Development Teams are self-organized and cross-functional.

Applying Scrum

Question

Every Development Team should have the competencies and skills needed to deliver a Done Increment in a Sprint.

Options

  • ATrue
  • BFalse

How the community answered

(36 responses)
  • A
    89% (32)
  • B
    11% (4)

Explanation

Development Teams are self-organized and cross-functional.

Topics

#cross-functional team#Definition of Done#Development Team competencies