PSM-II · Question #80

How should multiple Scrum Teams, working from the same Product Backlog, select the Product Backlog items their teams plan to work on?

The correct answer is A. The Product Owner will present the work and the Development Teams will select the items they. The ones doing the work are the best ones to decide what they can do and how to do it.

Scaling Scrum

Question

How should multiple Scrum Teams, working from the same Product Backlog, select the Product Backlog items their teams plan to work on?

Options

  • AThe Product Owner will present the work and the Development Teams will select the items they
  • BThe Product Owner creates separate Product Backlogs for each Development Team.
  • CEach Scrum Team would select an equal number of items.
  • DThe Product Owner assigns the work to each team.
  • EThe Scrum Team with the highest productivity will select the items first.

How the community answered

(26 responses)
  • A
    85% (22)
  • C
    4% (1)
  • D
    4% (1)
  • E
    8% (2)

Explanation

The ones doing the work are the best ones to decide what they can do and how to do it.

Topics

#multiple Scrum Teams#shared Product Backlog#Sprint Planning#scaling