Scrum
PSM-II · Question #72
PSM-II Question #72: Real Exam Question with Answer & Explanation
The correct answer is B. The Product Owner and the Development Team.. See the full explanation below for the reasoning.
Question
Who should be present to review and adjust the selected Sprint work if the Development Team determines that it will not be able to finish the complete forecast?
Options
- AThe stakeholders and Scrum Master.
- BThe Product Owner and the Development Team.
- CThe Development Team and Project Manager.
- DThe Scrum Master, the Business Analyst and the Development Team.
Community Discussion
No community discussion yet for this question.