What is the recommended size for a Development Team (within the Scrum Team)?

The correct answer is A. 3 to 9. According to the Scrum Guide, the Development Team should have between 3 and 9 members - small enough to stay agile and coordinate easily, yet large enough to complete meaningful work each Sprint without external dependencies. Why the distractors are wrong: B (Minimal 5)…

Applying Scrum

Question

What is the recommended size for a Development Team (within the Scrum Team)?

Options

  • A3 to 9
  • BMinimal 5
  • C7 plus or minus 2
  • D9

How the community answered

(33 responses)
  • A
    91% (30)
  • B
    6% (2)
  • D
    3% (1)

Explanation

According to the Scrum Guide, the Development Team should have between 3 and 9 members - small enough to stay agile and coordinate easily, yet large enough to complete meaningful work each Sprint without external dependencies.

Why the distractors are wrong:

  • B (Minimal 5) - Scrum sets a minimum of 3, not 5; smaller teams are allowed
  • C (7 ± 2) - This is Miller's Law from cognitive psychology, not a Scrum rule; it doesn't map to the actual guideline
  • D (9) - This is the maximum, not the fixed size; treating it as the answer confuses the upper bound with the entire range

Memory tip: Think "3 to 9 = enough to do the work, not too many to need a meeting about meetings." The boundaries exist for a reason: fewer than 3 creates skill gaps, more than 9 requires too much coordination overhead.