PSM-II · Question #71
What is the recommended size for a Development Team (within the Scrum Team)?
The correct answer is A. 3 to 9. According to the Scrum Guide, the Development Team should have between 3 and 9 members - small enough to stay agile and coordinate easily, yet large enough to complete meaningful work each Sprint without external dependencies. Why the distractors are wrong: B (Minimal 5)…
Question
What is the recommended size for a Development Team (within the Scrum Team)?
Options
- A3 to 9
- BMinimal 5
- C7 plus or minus 2
- D9
How the community answered
(33 responses)- A91% (30)
- B6% (2)
- D3% (1)
Explanation
According to the Scrum Guide, the Development Team should have between 3 and 9 members - small enough to stay agile and coordinate easily, yet large enough to complete meaningful work each Sprint without external dependencies.
Why the distractors are wrong:
- B (Minimal 5) - Scrum sets a minimum of 3, not 5; smaller teams are allowed
- C (7 ± 2) - This is Miller's Law from cognitive psychology, not a Scrum rule; it doesn't map to the actual guideline
- D (9) - This is the maximum, not the fixed size; treating it as the answer confuses the upper bound with the entire range
Memory tip: Think "3 to 9 = enough to do the work, not too many to need a meeting about meetings." The boundaries exist for a reason: fewer than 3 creates skill gaps, more than 9 requires too much coordination overhead.