The Product Owner's primary concern is the flow of value reflected in the ordering of the Product Backlog.
The correct answer is A. True. The Product Owner is also known as the value maximizer. He is responsible for maximizing the value of the work that the Development Team does. This is done through the ordering of the Product Backlog.
Applying Scrum
Question
The Product Owner's primary concern is the flow of value reflected in the ordering of the Product Backlog.
Options
- ATrue
- BFalse
How the community answered
(43 responses)- A93% (40)
- B7% (3)
Explanation
The Product Owner is also known as the value maximizer. He is responsible for maximizing the value of the work that the Development Team does. This is done through the ordering of the Product Backlog.
Topics
#Product Owner#Product Backlog ordering#value flow