PSM-II · Question #171

At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was…

The correct answer is A. The Development Team forecasts the most likely Product Backlog items to meet the business D. They discuss in the upcoming Sprint Retrospective why this happened and what changes will. All events are time-boxed events, such that every event has a maximum duration. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and…

Applying Scrum

Question

At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was able to clearly define the business objective he hopes to achieve in the Sprint. Which of the following two actions would you support? (Choose two.)

Options

  • AThe Development Team forecasts the most likely Product Backlog items to meet the business
  • BIf all agree they can extend the Sprint Planning until the Development Team can forecast enough
  • CAllow the Development Team members as much time as needed to review the Product Backlog
  • DThey discuss in the upcoming Sprint Retrospective why this happened and what changes will

How the community answered

(33 responses)
  • A
    82% (27)
  • B
    6% (2)
  • C
    12% (4)

Explanation

All events are time-boxed events, such that every event has a maximum duration. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal.

Topics

#Sprint Planning#Sprint Goal#unclear requirements#Product Backlog