PSM-II · Question #172

Steven is a Scrum Master on a new Scrum Team. What would be the best way for him to determine if the Product Owner is interacting enough with the Development Team during a Sprint?

The correct answer is C. See whether the Product Owner has provided enough information at the Sprint Planning to make. Outcomes of the Scrum Team are affected by the Product Owner's participation and availability. During a Sprint he/she is responsible for answering questions from the Development Team about items in the current Sprint and optimizing the value of the work the Development Team does.

Coaching & Mentoring

Question

Steven is a Scrum Master on a new Scrum Team. What would be the best way for him to determine if the Product Owner is interacting enough with the Development Team during a Sprint?

Options

  • ACheck whether the Product Owner is actively engaged at the Daily Scrums.
  • BCheck whether the Increment presented at the Sprint Review meets the Product Owner's
  • CSee whether the Product Owner has provided enough information at the Sprint Planning to make
  • DThe Product Owner must always be present with the Development Team. Unavailability of the

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    83% (20)
  • D
    4% (1)

Explanation

Outcomes of the Scrum Team are affected by the Product Owner's participation and availability. During a Sprint he/she is responsible for answering questions from the Development Team about items in the current Sprint and optimizing the value of the work the Development Team does.