Scrum
PSM-II · Question #17
PSM-II Question #17: Real Exam Question with Answer & Explanation
The correct answer is A. By removing impediments that hinder the Development Team and facilitating Development Team. The Scrum Master serves the Development Team by removing impediments to the Development Team's progress and facilitating Scrum events as requested or needed.
Question
In what ways does the Scrum Master keep a Development Team working at its highest level of productivity?
Options
- ABy removing impediments that hinder the Development Team and facilitating Development Team
- BBy helping the Development Team with user acceptance tests and tracking defects.
- CBy ensuring each member takes turns speaking at the Daily Scrum and ending the event on time.
- DBy keeping the Scrum board and burn-down chart updated daily.
Explanation
The Scrum Master serves the Development Team by removing impediments to the Development Team's progress and facilitating Scrum events as requested or needed.
Community Discussion
No community discussion yet for this question.