PSM-II · Question #159
By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team's Definition of Done. What two things should happen with the item? (Choose two.)
The correct answer is B. Do not include the item in the Increment for the Sprint. D. Estimate the remaining work needed to make it `done' and add it to the Product Backlog for the. At the end of a Sprint, the new Increment must be Done', which means it must be in useable condition and meet the Scrum Team's definition of Done'. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the…
Question
By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team's Definition of Done. What two things should happen with the item? (Choose two.)
Options
- AIt will be inspected at the Sprint Review and if it is acceptable by the stakeholders then include it
- BDo not include the item in the Increment for the Sprint.
- CSplit the item and add the estimation of the completed work to the current Sprint so not to impact
- DEstimate the remaining work needed to make it `done' and add it to the Product Backlog for the
How the community answered
(42 responses)- A2% (1)
- B95% (40)
- C2% (1)
Explanation
At the end of a Sprint, the new Increment must be Done', which means it must be in useable condition and meet the Scrum Team's definition of Done'. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the Definition of Done for the Scrum Team and it is used to assess when work is complete on the product Increment.