PSM-II · Question #101

PSM-II Question #101: Real Exam Question with Answer & Explanation

The correct answer is A. Sprint Retrospective. See the full explanation below for the reasoning.

Question

Which of the following is required in Scrum?

Options

  • ASprint Retrospective
  • BAll Development Team members answering the three questions at the Daily Scrum
  • CSprint Burndown Chart
  • DUser Stories
  • EAll of the above