PSM-II · Question #100
What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?
The correct answer is C. There is no acceptable reason. A new Sprint starts immediately after the conclusion of the. In Scrum, a new Sprint starts immediately after the previous one ends - there is no gap, no waiting period, and no role (including the Product Owner) has the authority to delay it; this is a core rule in the Scrum Guide. Option A is wrong because QA testing and release…
Question
What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?
Options
- AThe QA team has not finished testing the previous Increment before declaring it ready to ship.
- BThe stakeholders were disappointed with the Increment produced in the previous Sprint.
- CThere is no acceptable reason. A new Sprint starts immediately after the conclusion of the
- DThe Product Owner needs additional time to identify the next initiatives.
- EThere's not enough work in the Product Backlog to work on in the upcoming Sprint.
How the community answered
(52 responses)- A2% (1)
- C92% (48)
- D4% (2)
- E2% (1)
Explanation
In Scrum, a new Sprint starts immediately after the previous one ends - there is no gap, no waiting period, and no role (including the Product Owner) has the authority to delay it; this is a core rule in the Scrum Guide. Option A is wrong because QA testing and release decisions don't gate Sprint start - the Increment may already be "Done" by the team's Definition of Done regardless of shipping. Option B is wrong because stakeholder disappointment is handled through backlog refinement and Sprint Planning, not by pausing Scrum's cadence. Option D is wrong because identifying next initiatives is the Product Owner's ongoing responsibility during the Sprint, not a justification for a break between Sprints. Option E is wrong because if the backlog lacks sufficient work, that's a conversation for Sprint Planning - Scrum doesn't prescribe pausing; the team would plan with whatever is available.
Memory tip: Think of Sprints like heartbeats - the heart doesn't pause between beats, and neither does Scrum. Any answer suggesting a valid reason to delay a Sprint start is automatically wrong.