Scrum
PSM-II · Question #100
PSM-II Question #100: Real Exam Question with Answer & Explanation
The correct answer is C. There is no acceptable reason. A new Sprint starts immediately after the conclusion of the. See the full explanation below for the reasoning.
Question
What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?
Options
- AThe QA team has not finished testing the previous Increment before declaring it ready to ship.
- BThe stakeholders were disappointed with the Increment produced in the previous Sprint.
- CThere is no acceptable reason. A new Sprint starts immediately after the conclusion of the
- DThe Product Owner needs additional time to identify the next initiatives.
- EThere's not enough work in the Product Backlog to work on in the upcoming Sprint.
Community Discussion
No community discussion yet for this question.