nerdexam
Scrum

PSM-II · Question #100

PSM-II Question #100: Real Exam Question with Answer & Explanation

The correct answer is C. There is no acceptable reason. A new Sprint starts immediately after the conclusion of the. See the full explanation below for the reasoning.

Question

What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?

Options

  • AThe QA team has not finished testing the previous Increment before declaring it ready to ship.
  • BThe stakeholders were disappointed with the Increment produced in the previous Sprint.
  • CThere is no acceptable reason. A new Sprint starts immediately after the conclusion of the
  • DThe Product Owner needs additional time to identify the next initiatives.
  • EThere's not enough work in the Product Backlog to work on in the upcoming Sprint.

Community Discussion

No community discussion yet for this question.

Full PSM-II Practice