PSM-II · Question #100

What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?

The correct answer is C. There is no acceptable reason. A new Sprint starts immediately after the conclusion of the. In Scrum, a new Sprint starts immediately after the previous one ends - there is no gap, no waiting period, and no role (including the Product Owner) has the authority to delay it; this is a core rule in the Scrum Guide. Option A is wrong because QA testing and release…

Applying Scrum

Question

What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?

Options

  • AThe QA team has not finished testing the previous Increment before declaring it ready to ship.
  • BThe stakeholders were disappointed with the Increment produced in the previous Sprint.
  • CThere is no acceptable reason. A new Sprint starts immediately after the conclusion of the
  • DThe Product Owner needs additional time to identify the next initiatives.
  • EThere's not enough work in the Product Backlog to work on in the upcoming Sprint.

How the community answered

(52 responses)
  • A
    2% (1)
  • C
    92% (48)
  • D
    4% (2)
  • E
    2% (1)

Explanation

In Scrum, a new Sprint starts immediately after the previous one ends - there is no gap, no waiting period, and no role (including the Product Owner) has the authority to delay it; this is a core rule in the Scrum Guide. Option A is wrong because QA testing and release decisions don't gate Sprint start - the Increment may already be "Done" by the team's Definition of Done regardless of shipping. Option B is wrong because stakeholder disappointment is handled through backlog refinement and Sprint Planning, not by pausing Scrum's cadence. Option D is wrong because identifying next initiatives is the Product Owner's ongoing responsibility during the Sprint, not a justification for a break between Sprints. Option E is wrong because if the backlog lacks sufficient work, that's a conversation for Sprint Planning - Scrum doesn't prescribe pausing; the team would plan with whatever is available.

Memory tip: Think of Sprints like heartbeats - the heart doesn't pause between beats, and neither does Scrum. Any answer suggesting a valid reason to delay a Sprint start is automatically wrong.

Topics

#Sprint cadence#Product Owner#Sprint start#continuous delivery