Scrum
PSM-I · Question #46
When does the second Sprint start?
The correct answer is C. Immediately after the first Sprint. The correct answer is C, because the second Sprint starts immediately after the first Sprint. The Scrum Guide states that "Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint."
Submitted by the_admin· Apr 18, 2026Scrum Framework
Question
When does the second Sprint start?
Options
- AOnce the architectural changes for the second Sprint have been approved by the senior architect.
- BAfter the Product Backlog for the second Sprint has been selected.
- CImmediately after the first Sprint.
- DAfter the customer completes acceptance testing of the first Sprint.
How the community answered
(56 responses)- A5% (3)
- B2% (1)
- C86% (48)
- D7% (4)
Explanation
The correct answer is C, because the second Sprint starts immediately after the first Sprint. The Scrum Guide states that "Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint."
Topics
#Sprint Cadence#Scrum Events#Sprint Sequencing#Time-boxing
Community Discussion
No community discussion yet for this question.