PSM-I · Question #45
When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
The correct answer is B. False. The correct answer is B, because when multiple teams work together on the same product, they should not maintain separate Product Backlogs. The Scrum Guide states that "multiple Scrum Teams often work together on the same product. One product goal unites them. Therefore, they…
Question
When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
Options
- ATrue
- BFalse
How the community answered
(35 responses)- A9% (3)
- B91% (32)
Explanation
The correct answer is B, because when multiple teams work together on the same product, they should not maintain separate Product Backlogs. The Scrum Guide states that "multiple Scrum Teams often work together on the same product. One product goal unites them. Therefore, they must mutually define and comply with a definition of ‘Done' that applies to their combined work product. ... Multiple Scrum Teams working on the same product use the same Product Backlog."
Topics
Community Discussion
No community discussion yet for this question.