The correct answer is E: The Product Owner.. The Product Owner is responsible for engaging the stakeholders, as stated in the Scrum Guide1: "The Product Owner is one person, not a committee. The Product Owner may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog item'
Question
Who is responsible for engaging the stakeholders?
Options
- AThe Business Analyst.
- BThe Development Team.
- CThe Team Manager.
- DThe Project Manager.
- EThe Product Owner.
Explanation
The Product Owner is responsible for engaging the stakeholders, as stated in the Scrum Guide1: "The Product Owner is one person, not a committee. The Product Owner may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog item's priority must address the Product Owner."