PSM-I · Question #59
Who is responsible for engaging the stakeholders?
The correct answer is E. The Product Owner. The Product Owner is responsible for engaging the stakeholders, as stated in the Scrum Guide1: "The Product Owner is one person, not a committee. The Product Owner may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog…
Question
Who is responsible for engaging the stakeholders?
Options
- AThe Business Analyst.
- BThe Development Team.
- CThe Team Manager.
- DThe Project Manager.
- EThe Product Owner.
How the community answered
(44 responses)- A5% (2)
- B7% (3)
- D2% (1)
- E86% (38)
Explanation
The Product Owner is responsible for engaging the stakeholders, as stated in the Scrum Guide1: "The Product Owner is one person, not a committee. The Product Owner may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog item's priority must address the Product Owner."