The correct answer is E: The Product Owner.. The Product Owner is responsible for engaging the stakeholders, as stated in the Scrum Guide1: "The Product Owner is one person, not a committee. The Product Owner may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog item'

Submitted by kevin_r· Apr 18, 2026Managing Products with Agility

Question

Who is responsible for engaging the stakeholders?

Options

  • AThe Business Analyst.
  • BThe Development Team.
  • CThe Team Manager.
  • DThe Project Manager.
  • EThe Product Owner.

Explanation

The Product Owner is responsible for engaging the stakeholders, as stated in the Scrum Guide1: "The Product Owner is one person, not a committee. The Product Owner may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog item's priority must address the Product Owner."

Topics

#Product Owner#Stakeholder Management#Scrum Roles#Accountability