PSM-I · Question #37
PSM-I Question #37: Real Exam Question with Answer & Explanation
The correct answer is A: Turn Product Backlog items into an Increment of potentially releasable product functionality.. According to the Scrum Guide, an Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, an Increment must be usable. Multipl
Question
The Development Team should have all the skills needed to:
Options
- ATurn Product Backlog items into an Increment of potentially releasable product functionality.
- BDo all of the development work, except for specialized testing that requires additional tools and
- CComplete the project within the date and cost as calculated by the Product Owner.
Explanation
According to the Scrum Guide, an Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, an Increment must be usable. Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value. Therefore, in order to turn Product Backlog items into an Increment of potentially releasable product functionality, the Development Team should have all the skills needed.
Topics
Community Discussion
No community discussion yet for this question.