PSM-I · Question #183
What should be taken into account for the Definition of "Done"? Select the two most appropriate items.
The correct answer is B. Conventions, standards and guidelines of the Organization D. Definition of "Done" of other Scrum Teams working on the same Product. Two inputs must be considered when creating a Definition of Done: (B) Conventions, standards, and guidelines of the Organization - organizational standards (e.g., coding standards, compliance requirements, security policies) must be incorporated into the DoD to ensure the…
Question
What should be taken into account for the Definition of “Done”? Select the two most appropriate items.
Options
- ADefinition of "Done" of other Scrum Teams working on other products
- BConventions, standards and guidelines of the Organization
- CAdvice of the Scrum Master
- DDefinition of "Done" of other Scrum Teams working on the same Product
- EExperience of the Product Owner
How the community answered
(36 responses)- A6% (2)
- B89% (32)
- C3% (1)
- E3% (1)
Explanation
Two inputs must be considered when creating a Definition of Done: (B) Conventions, standards, and guidelines of the Organization - organizational standards (e.g., coding standards, compliance requirements, security policies) must be incorporated into the DoD to ensure the Increment meets enterprise-wide quality requirements; (D) Definition of Done of other Scrum Teams working on the same Product - when multiple teams contribute to the same product, their DoDs must be compatible and ideally aligned so the integrated Increment meets a consistent quality bar. Option A (other teams on other products) is irrelevant. Options C (Scrum Master advice) and E (Product Owner experience) are not formally defined inputs in the Scrum Guide.