Question
Which outcome is expected as Scrum Teams mature?
Options
- AThey will improve their definition of "Done" to include more stringent criteria.
- BThe Sprint Retrospectives will grow to be longer than 4 hours.
- CThere is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.
- DSprint Reviews will no longer be needed.
- EA Scrum Master is no longer needed since they are a mature team now.