PSM-I · Question #220
Which two things should the Development Team do during the first Sprint? (Choose two.)
The correct answer is C. Develop at least one piece of functionality. E. Create an increment of potentially releasable software. According to the Scrum Guide, the Development Team should do two things during the first develop at least one piece of functionality and create an increment of potentially releasable software. These are the goals of every Sprint, regardless of its order. The other options are…
Question
Which two things should the Development Team do during the first Sprint? (Choose two.)
Options
- AMake up a plan for the rest of the project.
- BAnalyze, describe, and document the requirements for the subsequent Sprints.
- CDevelop at least one piece of functionality.
- DDefine the major product features and release plan architecture
- ECreate an increment of potentially releasable software.
How the community answered
(29 responses)- A3% (1)
- B7% (2)
- C86% (25)
- D3% (1)
Explanation
According to the Scrum Guide, the Development Team should do two things during the first develop at least one piece of functionality and create an increment of potentially releasable software. These are the goals of every Sprint, regardless of its order. The other options are not things that the Development Team should do during the first Sprint, as they are either out of scope (such as making a plan for the rest of the project or defining major product features and release plan architecture) or unnecessary (such as analyzing, describing, and documenting requirements for subsequent Sprints).
Topics
Community Discussion
No community discussion yet for this question.