PSM-I · Question #173
Which of these may a Development Team deliver at the end of a Sprint?
The correct answer is C. An increment of working software that is "done". The correct answer is C, because a Development Team should deliver an increment of working software that is "done" by the end of a Sprint. The Scrum Guide states that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the…
Question
Which of these may a Development Team deliver at the end of a Sprint?
Options
- AFailing unit tests, to identify acceptance tests for the next Sprint.
- BAn increment of software with minor known bugs in it.
- CAn increment of working software that is "done".
- DA single document, if that is what the Scrum Master asked for.
How the community answered
(25 responses)- A4% (1)
- B8% (2)
- C88% (22)
Explanation
The correct answer is C, because a Development Team should deliver an increment of working software that is "done" by the end of a Sprint. The Scrum Guide states that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints. At the end of a Sprint, the new Increment must be ‘Done,' which means it must be in useable condition and meet the Scrum Team's definition of ‘Done'."
Topics