PSM-I · Question #36

During a Sprint Retrospective, for what is the Scrum Master responsible?

The correct answer is B. Participating as a Scrum team member and facilitating as requested or needed. The Scrum Master participates as a full Scrum team member and facilitates as requested or needed (B). The Sprint Retrospective belongs to the entire Scrum Team-the Scrum Master is not a neutral outside facilitator but an equal participant who also inspects and adapts. They…

Submitted by yuriko_h· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

During a Sprint Retrospective, for what is the Scrum Master responsible?

Options

  • APrioritizing the resulting action items.
  • BParticipating as a Scrum team member and facilitating as requested or needed.
  • CActing as a scribe to capture the Development Team's answers.
  • DSummarizing and reporting the discussions to management.

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    91% (53)
  • C
    2% (1)
  • D
    2% (1)

Explanation

The Scrum Master participates as a full Scrum team member and facilitates as requested or needed (B). The Sprint Retrospective belongs to the entire Scrum Team-the Scrum Master is not a neutral outside facilitator but an equal participant who also inspects and adapts. They facilitate when it helps, but the team may self-facilitate. Prioritizing action items (A) is the team's collective responsibility. Acting only as a scribe (C) is too passive and removes the Scrum Master from meaningful participation. Reporting to management (D) violates the retrospective's safe-to-speak environment and Scrum's principle that this meeting is for the team.

Topics

#Scrum Master Role#Sprint Retrospective#Facilitation#Scrum Events