When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint? (Choose the best answer)

The correct answer is B. At the Sprint Planning Evented. According to the Scrum Guide, a Developer becomes accountable for the value of a Product Backlog item selected for the Sprint at the Sprint Planning event. This is when the Developers select items from the Product Backlog that they can commit to complete within a Sprint. The…

Submitted by kim_seoul· Apr 18, 2026Scrum Framework

Question

When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint? (Choose the best answer)

Options

  • ANever The entire Scrum Team is accountable for creating value every Sprint.
  • BAt the Sprint Planning Evented
  • CWhenever a team member can accommodate more worn.
  • DDuring the Daily scrum

How the community answered

(15 responses)
  • B
    93% (14)
  • D
    7% (1)

Explanation

According to the Scrum Guide, a Developer becomes accountable for the value of a Product Backlog item selected for the Sprint at the Sprint Planning event. This is when the Developers select items from the Product Backlog that they can commit to complete within a Sprint. The Developers are then responsible for creating a valuable Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they either imply that Developers are not accountable for value (such as never or whenever), or that they become accountable at a different time (such as during the Daily Scrum).

Topics

#Sprint Planning#Developer Accountability#Product Backlog Item Selection#Scrum Events

Community Discussion

No community discussion yet for this question.