True or False: An increment must be released to customers or users at the end of each sprint.
The correct answer is B. False. According to the Scrum Guide, an Increment does not have to be released to customers or users at the end of each Sprint. However, it must be in a usable condition and meet the Definition of Done. The decision to release an Increment is made by the Product Owner, based on the…
Question
True or False: An increment must be released to customers or users at the end of each sprint.
Options
- ATrue
- BFalse
How the community answered
(27 responses)- A7% (2)
- B93% (25)
Explanation
According to the Scrum Guide, an Increment does not have to be released to customers or users at the end of each Sprint. However, it must be in a usable condition and meet the Definition of Done. The decision to release an Increment is made by the Product Owner, based on the value and feedback obtained from stakeholders. The other option is not valid, as it implies that releasing an Increment is mandatory at the end of each Sprint.
Topics
Community Discussion
No community discussion yet for this question.