The correct answer is C: Bring up the problem in the Sprint Retrospective.. The Scrum Master serves the Product Owner by coaching them on effective practices and Scrum values, and serves the team by facilitating improvement. Option D (coaching the PO in Scrum values and incremental delivery) is the Scrum Master's primary accountability here - the PO need
Question
The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)
Options
- AInform the Product Owner's functional manager.
- BStop the Sprint, send the Product Owner to a course and restart.
- CBring up the problem in the Sprint Retrospective.
- DCoach the Product Owner in the values of Scrum and incremental delivery.
- ENominate a proxy Product Owner.
Explanation
The Scrum Master serves the Product Owner by coaching them on effective practices and Scrum values, and serves the team by facilitating improvement. Option D (coaching the PO in Scrum values and incremental delivery) is the Scrum Master's primary accountability here - the PO needs to understand that collaboration during the Sprint is essential for clarifying requirements and enabling the team to deliver value. Option C (raising the problem in the Sprint Retrospective) is appropriate because the Retrospective is the formal ceremony for the team to inspect and adapt its process. Option A (informing the manager) bypasses the Scrum process and is not aligned with Scrum values - the Scrum Master should not escalate to functional management. Option B (stopping the Sprint) is an extreme overreaction. Option E (nominating a proxy PO) introduces an anti-pattern and avoids solving the root cause.