Question
A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?
Options
- AThe hiring manager is responsible, because he/she hired the developer.
- BThe Scrum Manager is responsible, because he/she removes Impediments.
- CThe Development Team is responsible, and may need help from the Scrum Master.
- DThe Product Owner is responsible, because he/she controls the return on investment (ROI).
Unlock PSM-I to see the answer
You've previewed enough free PSM-I questions. Unlock PSM-I for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Self-managing Teams#Scrum Master Role#Team Conflict Resolution#Development Team Responsibilities