The correct answer is B: How to best accomplish its work.. According to the Scrum Guide, a self-organizing Development Team chooses how to best accomplish its work, rather than being directed by others outside the team. The other options are not choices that a self-organizing Development Team makes, as they are either determined by the S

Submitted by daniela_cl· Apr 18, 2026Developing People and Teams

Question

Which does a self-organizing Development Team choose?

Options

  • ASprint length.
  • BHow to best accomplish its work.
  • CStakeholders for the Sprint Review.
  • DWhen to release, based on its progress.
  • EProduct Backlog ordering.

Explanation

According to the Scrum Guide, a self-organizing Development Team chooses how to best accomplish its work, rather than being directed by others outside the team. The other options are not choices that a self-organizing Development Team makes, as they are either determined by the Scrum framework (such as Sprint length and Product Backlog ordering) or by collaboration with other roles (such as stakeholders for the Sprint Review and when to release).

Topics

#Self-organizing teams#Development Team responsibilities#Scrum Team empowerment

Community Discussion

No community discussion yet for this question.

Full PSM-I PracticeBrowse All PSM-I Questions